NBN CO. Announces Long Delay Until New Homes Served Wednesday, 23 November 2011

NBN Co. has just advised us that they cannot connect fibre to homes in new greenfield estates until 6 months after civil construction has been completed. This is quite unrealistic and unacceptable. But there is a solution, if NBN Co. is interested. ... see more

Telstra certificate for plan-sealing Thursday, 11 August 2011

Plan sealing will now be delayed by 6-8 weeks. Telstra will not issue an Infrastructure Provisioning Confirmation until its conduits and pits have been installed. Telstra issues two certificates when they have been engaged to design/install conduits and pits: An Infrastructure Provisioning ... see more

NBN Fact Sheet Tuesday, 5 April 2011

NBN Co has just published a helpful Fact Sheet which explains how fibre will be installed in greenfields developments. It can be downloaded here ... see more